News about construction of Residential complex “BEREZKI”
|
|
As of May 20, 2008 a series of works of constructing the first line of the complex were finished.
The following works are commenced:
1. construction of monolithic reinforced concrete grill of House №1;
2. reconstruction of electric power substation units; laying of electric cable and construction of a new transformer substation for autonomous electric power supply to the residential district;
3. construction of concrete blinding coat for monolithic reinforced concrete grill of House №2.
Furthermore, second line construction works are commenced: geological survey and enclosure preparation works.
The following works are completed:
· preparation stage works of the first construction line (relocation of engineering services – water conduit, electric cable beyond boundaries of the construction site; territory enclosure; arrangement of temporary roads and sites);
· construction of pile field of House №2.
|