BEREZKI Complex construction report for October 2008
|
|
In the period October 01 – November 01, 2008 at the construction site of Residential complex “Berezki” in Vyshgorod town works of monolithic frame construction, interior separation wall blockwork and electrical mounting works in residential building №1 were performed.
Floor 9 slab construction works were finished, with 108.73 m3 of concrete (В30 class) used, mounting of pillars, pylons, diaphragms and floor slabs on Floors 10 and 11 was completed and vertical elements mounted on Floor 12. In addition to that, 125.575 tons of hot-rolled reinforcing steel of classes А240 and А400 was used. The area of one floor slab from Floor 8 to Floor 15 is 815.8 m2. Apartment separation walls of Floors 2, 3 and 4 were constructed using aerated concrete blocks of 28.09 m3, 28.09 m3 and 18.82 m3, respectively.
As of November 10, 2008, at the construction site of Residential complex “Berezki” works of vertical elements (pillars, pylons and diaphragms) installation on Floor 13 are underway. Monolithic works in the building in general have been completed approximately at the level of 70%.
|