Zero cycle of the first line of BEREZKI Complex
|
|
Construction of zero cycle of the first line of BEREZKI Complex is almost finished.
As of June 25, the following works are underway:
1. construction of walls and pillars of the basement of House №1;
2. construction of monolithic reinforced concrete grill of House №2;
3. installation works at transformer substation of "BEREZKI" residential district;
4. preparations of the second line construction site.
The following works are finished:
1. pile field construction of Houses №1 and №2;
2. construction of concrete blinding coat of Houses №1 and №2;
3. transformer substation construction works;
4. construction of monolithic reinforced concrete grill of House №1;
5. reconstruction of electric power substation units.
|